There are two separate construction jobs on Blenheim Boulevard, and they finish at different times. The City's rebuild of the road from Layton Hall Drive to Ridge Avenue is scheduled to take about two years from its July 2026 start. The Willard-Sherwood Health & Community Center going up at 3750 Blenheim Blvd has a move-in target of fall 2029. So the cones on the road will likely be gone well before the fencing by the Sherwood Center comes down. If you drive, walk or ride the bus on this street, that gap changes how you plan the next three years.
This winter is when both jobs are at their busiest on the same few blocks.
Two crews, two contracts, two finish lines
The road project is a City transportation job. City Council awarded the $21,770,570 construction contract to Fort Myer Construction Corporation. The building project is a city-county partnership. Grimm + Parker is the architect, The Christman Company is the general contractor, and Fairfax County is paying $73.4 million of the $127 million construction cost, FFXnow reported.
| Blenheim Boulevard Multimodal Improvements | Willard-Sherwood Health & Community Center | |
|---|---|---|
| Where | Blenheim Blvd, Layton Hall Dr to Ridge Ave | 3750 Blenheim Blvd, next to the Sherwood Center |
| Started | On or after July 6, 2026 | Fencing went up in August; groundbreaking Sept. 30, 2026 |
| Expected length | About two years | Move-in targeted for fall 2029 |
| What you'll notice | Lane shifts, a 25 mph limit, short-term sidewalk closures | A closed walking path, a closed sidewalk, fencing near the Sherwood entrance |
The City's two pages don't quite agree on the building's finish date. The Willard-Sherwood project page still says "Summer 2029." The newer construction schedule presented at the Sept. 3 community meeting, and repeated at the groundbreaking, says fall 2029. Fall 2029 is the safer date for planning.
The City's Blenheim Boulevard project page says the two jobs are being coordinated "to maintain traffic flow," along with a planned bridge deck rehabilitation near Ridge Avenue. The City hasn't posted dates for the bridge work yet.
Why this winter is the crowded stretch
Put the two published schedules side by side and they overlap through the cold months:
- Now through December 2026. Utility relocation for Willard-Sherwood, scheduled September through December.
- October and November 2026. Demolition of the old Joseph Willard Health Center. Crews were already tearing the building down during the Sept. 30 ceremony.
- July 2026 to about January 2027. Phase 1 of the road project, based on the City's approximate sequence map.
- Winter 2026 to spring 2027. Mass excavation at the Willard-Sherwood site.
- About January to December 2027. Phase 2 of the road project.
The road work moves from side to side. It starts on the south side, the Daniels Run side, for new asphalt. Then it moves to the north side for curb, gutter and other work, and then goes back south. While crews work one side, traffic shifts to the other. The phase dates are labeled approximate, so a lane pattern you got used to in October may not be there in February.
A few things stay the same whatever phase the road is in. The City expects Blenheim to stay open through construction, apart from short announced closures, with periodic lane closures, lane shifts and temporary detours, mostly during off-peak hours. Roadway work runs Monday through Friday, 9 a.m. to 3 p.m. Work off the roadway can run from 7 a.m. to 5 p.m. Any night or weekend work is supposed to be posted on the project website and along the corridor ahead of time. The 25 mph signs went up the weekend of August 14, down from 30 mph, and the limit goes back to 30 when the project is done. The City also says access to every home, side street and business will be kept open. If a crew needs to block a driveway briefly, it will talk to the owner first.
Full closures have happened, and with warning. In mid-August the City shut Blenheim for two days to remove trees. FFXnow's coverage of that closure also covered single-lane closures with flaggers alternating traffic through the work zone. The easiest way to hear about the next one is the City's construction text alert. Text BBLVD to 844-543-4554.
The detour that lasts longest is on foot
The longest-running change on the corridor is a closed walking route. On Aug. 3, the Willard-Sherwood project closed the walking path that runs between the Sherwood Center and the police station and connects to Layton Hall Apartments. The sidewalk along Layton Hall Drive next to the old health center closed too. The City expects that construction zone to stay in place for about three years, through fall 2029. It has posted a map of alternate walking routes from Layton Hall to nearby schools and asks families who use these paths to allow extra travel time.
That means the walking detour will very likely still be in place after the road rebuild finishes. Someone who walks from Layton Hall toward Blenheim in 2028 may get new sidewalks and a cycle track on the boulevard and still have to go around the fenced lot to reach them.
The Sherwood Center is still open. The Stacy C. Sherwood Community Center at 3740 Blenheim Blvd keeps running through construction, according to FFXnow's groundbreaking report. Expect fencing near its entrance, which went up in August while underground utilities were moved. The Young at Heart Senior Center is staying at Green Acres Center, 4401 Sideburn Road, during construction. If you used to go to the Willard building for county health services, that building closed Oct. 1, 2025. Fairfax County now points residents to its other Health Department clinics, including Franconia-Springfield. The Sept. 3 community meeting presentation lists them as Annandale at 7611 Little River Turnpike, Franconia-Springfield at 6564 Loisdale Court, Herndon-Reston at 1850 Cameron Glen Drive, and Mount Vernon at 8350 Richmond Highway.
Buses, holidays and the busiest weekend on the corridor
CUE buses keep running on Blenheim through construction. Some stops may move short distances for safety, and the City says to look for signs at your usual stop. During the August closure, stops between Lion Run and Fairfax Circle were out of service and the Gold 1 and Gold 2 routes were detoured. That shows how a closure can reach the buses, but those detours have ended. The CUE holiday schedule affects every route, not just Blenheim:
- Nov. 11 and Nov. 27: modified service, one bus per route
- Nov. 26, Thanksgiving Day: no CUE service
- Dec. 24, Christmas Eve: weekday service ends at 7 p.m.
- Dec. 25, Christmas Day: no CUE service
The weekend that puts the most people on this stretch is coming up. The City's 40th Annual Holiday Craft Show is Nov. 21 and 22 at Fairfax High School, 10 a.m. to 5 p.m. Saturday and 10 a.m. to 3 p.m. Sunday. It falls on a weekend, outside regular roadway work hours. Parking is available at the school both days. On Saturday only, the City runs a free, accessible shuttle from 9:30 a.m. to 5:30 p.m. between WillowWood Plaza and the school, and recommends it if the lot fills. If you live along Blenheim, Saturday may be the day to use the shuttle rather than drive the corridor.
What the street turns into
The road project replaces Blenheim between Layton Hall Drive and Ridge Avenue with a street that has one travel lane in each direction and:
- A two-way, 10-foot-wide cycle track on the north side
- 5-foot-wide sidewalks on both sides
- Two multimodal hubs with upgraded bus shelters, bikeshare stations and bike racks
- A new roundabout at Ridge Avenue
- New left-turn lanes at Daniels Run Elementary, Sherwood Center and Great Oaks Drive
- An outdoor classroom and community amphitheater outside Fairfax High School
- Pedestrian-scale lighting and landscaping
The City says the design came out of more than 20 years of planning and public input. Once the Willard-Sherwood building opens, the other end of the corridor gets a building about three times the size of the 1950s health center it replaces. Plans include a fitness center, a full-size gym, a track, classrooms, a dedicated youth area and a rooftop plaza, along with the Young at Heart Senior Center, which will move from Green Acres. A two-level underground garage handles parking. The building will connect to the existing Sherwood Center. City parks director Stacey Sommerfield told FFXnow that the City is "so excited to bring all our services under one roof."
The City's own schedules put the road work ending first, with the walking detour at Layton Hall lasting until fall 2029. For questions before then, the City lists Transportation Capital Project Manager Sunny Sarna at 703-273-3067, the Department of Public Works at 703-385-7810, and an online reporting tool at fairfaxva.gov/resolve.
If you own a home near Blenheim and want a clear picture of where its value stands while the street is being rebuilt, Jonathan Rundlett is glad to talk it through. Request a free home valuation and we'll go over the numbers with the corridor's timeline in view.